Do you need footings for a shed?
Usually not. A shed on pressure-treated skids rests on a gravel pad or on blocks set on tamped gravel. If frost lifts the ground in winter, the shed rides up with it and settles back in spring, which a small building on skids shrugs off. You need real footings when:
- Your town requires them. Some building departments ask for footings below the frost line once a shed needs a permit, or above a certain size. See do you need a permit for a shed?
- The site is steep. Piers stand at different heights, so you don't have to dig the high side down by a foot or more.
- The doors must stay square. In cold areas with heavy frost heave, a shed that moves each winter can leave its doors binding. Footings below the frost line stop that.
Three kinds of shed footing
| Footing | What it is | Best for | Price each |
|---|---|---|---|
| Concrete deck blocks | Precast blocks set on tamped gravel; the skid sits on top | Level or gently sloping ground, no frost rules | $9.49 |
| Solid concrete blocks | 4 x 8 x 16 in solid blocks laid flat on tamped gravel, stacked on the low side of a slope | The cheapest support on firm ground | $2.29 |
| Poured concrete piers | Concrete in a cardboard form tube, from below the frost line to 2 in above the ground | Slopes, frost heave and towns that require footings | 4 bags and a tube for a 10 in pier 3 ft deep: $37.95 |
How many footings does a shed need?
One under each skid at each end, and more in between so that no two are more than 4 ft apart; any further and the 4x4 skids can sag. Sheds up to 10 ft wide sit on 3 skids and 12 ft wide sheds on 4, as in our plans. The table prices each kind of footing for every plan size, with the piers 10 in across and 3 ft deep.
| Shed | Footings | Deck blocks | Solid blocks | Piers, 10 in x 3 ft |
|---|---|---|---|---|
| 6x8 | 9 (3 x 3) | $85 | $21 | $306 (29 bags) |
| 8x8 | 9 (3 x 3) | $85 | $21 | $306 (29 bags) |
| 8x10 | 12 (3 x 4) | $114 | $27 | $401 (38 bags) |
| 8x12 | 12 (3 x 4) | $114 | $27 | $401 (38 bags) |
| 8x16 | 15 (3 x 5) | $142 | $34 | $502 (48 bags) |
| 10x10 | 12 (3 x 4) | $114 | $27 | $401 (38 bags) |
| 10x12 | 12 (3 x 4) | $114 | $27 | $401 (38 bags) |
| 10x14 | 15 (3 x 5) | $142 | $34 | $502 (48 bags) |
| 10x16 | 15 (3 x 5) | $142 | $34 | $502 (48 bags) |
| 12x12 | 16 (4 x 4) | $152 | $37 | $534 (51 bags) |
| 12x16 | 20 (4 x 5) | $190 | $46 | $667 (64 bags) |
The lean-to sheds are named depth first: an 8x12 lean-to is 12 ft wide and 8 ft deep, so it sits on 4 skids 8 ft long, 12 footings in all. Pier prices include a form tube for each pier, the concrete, and an anchor bolt in each corner pier. On a slope, add the extra blocks you stack on the low side. The shed foundation calculator counts the blocks for any size: choose “Concrete blocks under the skids”.
How deep should shed footings be?
Below the frost line, if the reason for footings is frost. That depth is set locally and runs from a few inches along the Gulf Coast to 48 in or more across the northern states, so ask your building department for the number. Dig each hole 4 in deeper still for a bed of tamped gravel. Blocks and deck blocks only need to sit on firm subsoil, never on topsoil.
Concrete for one pier, in 80 lb bags, poured 2 in above the ground, with 10% to spare:
| Pier diameter | 2 ft deep | 3 ft deep | 4 ft deep |
|---|---|---|---|
| 8 in | 2 bags | 3 bags | 3 bags |
| 10 in | 3 bags | 4 bags | 5 bags |
| 12 in | 4 bags | 5 bags | 6 bags |
The concrete calculator works out any other size: choose “Round column or post hole”. For a whole row of piers, enter the count there rather than multiplying, so the waste allowance is shared.
What shed footings cost
For a 10x12 shed, the 12 supports come to $27 as solid blocks, $114 as deck blocks, or $401 as 10 in piers 3 ft deep, which take 38 bags of concrete. A 12x16 needs 20 and costs $46, $190 or $667. The prices are the regular shelf prices at Sutherlands in Harrisonville, Missouri on November 22, 2026: 80 lb concrete at $6.24 a bag, deck blocks at $9.49, solid blocks at $2.29, form tubes 48 in long from $12.99 and anchor bolts at $1.99. Renting a gas auger for a day saves a lot of digging for a dozen or more holes.
How to pour pier footings for a shed
- Call 811 a few days before you dig, so buried lines get marked. It's free.
- Lay out the skid lines. Run a string for each skid, square to each other, with the outside strings under the walls. Mark a hole at each end of every string and every 4 ft or less between.
- Dig the holes a few inches wider than the tube and 4 in deeper than the pier, then tamp 4 in of gravel into the bottom of each.
- Set the tubes plumb, cut so the tops all stand at the same height, 2 in above the highest ground. A string pulled tight across the tops, checked with a line level, shows when they match. Backfill around the tubes and tamp the soil.
- Fill the tubes with concrete, poking a stick up and down as you go to let the air out. Strike the top off flat with the tube.
- Set an anchor bolt in the middle of each corner pier while the concrete is wet, with enough thread left to pass through the skid.
- Let it cure for a few days, peel the tube off above ground, then set the skids on the piers, bolt the corners down, and build the floor frame on top.
Quick answers
Does a shed need footings?
Most storage sheds don't. A shed on skids rests on a gravel pad or on blocks. Footings below the frost line are for steep sites, heavy frost heave and towns that require them, so ask your building department first.
How deep should shed footings be?
Below your area's frost line, which your building department can tell you. It ranges from a few inches in the far South to 48 in or more in the North. Blocks and deck blocks only need firm subsoil under a few inches of tamped gravel.
How many footings does a 10x12 shed need?
12: 4 under each of its 3 skids, at each end and no more than 4 ft apart. A 12x16 shed needs 20.
How far apart should shed footings be?
No more than 4 ft apart along each skid, with one under each end, so the 4x4 skids don't sag in between.
Are deck blocks good enough for a shed?
Yes, on firm, level ground where the town doesn't require frost footings. Set each one on a few inches of tamped gravel on subsoil, not topsoil, and level them all to one string line.
How many bags of concrete for a shed footing?
4 bags of 80 lb mix for a 10 in pier 3 ft deep, standing 2 in above the ground. A 10x12 shed's 12 piers take 38 bags in all.