How the gravel pad is worked out
The pad is bigger than the shed so that rain running off the roof lands on stone. A foot on every side is the usual allowance, and it is what our shed plans use.
Pad width = shed width + 2 × border
Pad length = shed length + 2 × border
Volume (ft³) = pad width × pad length × (depth in inches ÷ 12)
Stone to order = volume × (1 + extra %), in cubic yards (÷ 27)
Weight = about 100 lb per ft³ of crushed stone, or 1.35 tons per cubic yard
Worked example: a 10 × 12 ft shed
- Pad size: 10 + 2 = 12 ft wide and 12 + 2 = 14 ft long.
- Volume at 4 in deep: 12 × 14 × (4 ÷ 12) = 56 ft³.
- With 10% extra for compaction: 61.6 ft³, which is 2.28 yd³.
- Rounded up to what you can order: 2.3 cubic yards, weighing about 3.08 tons.
- At $49 a cubic yard, that is $112.70 before delivery.
Gravel for common shed sizes
A 4 in pad of 3/4 in crushed stone, a foot past the shed on every side, with 10% extra for compaction. The cost is at $49 a cubic yard, the middle of what 200 yards across the US published for crushed stone in the GoodGravel Gravel Price Index for November 2026. Delivery is extra.
| Shed | Pad size | Stone to order | Weight | Stone cost |
|---|---|---|---|---|
| 6x8 | 8 x 10 ft | 1.1 cubic yards | 1.47 tons | $53.90 |
| 8x8 | 10 x 10 ft | 1.4 cubic yards | 1.83 tons | $68.60 |
| 8x10 | 10 x 12 ft | 1.7 cubic yards | 2.2 tons | $83.30 |
| 8x12 | 10 x 14 ft | 2 cubic yards | 2.57 tons | $98.00 |
| 10x10 | 12 x 12 ft | 2 cubic yards | 2.64 tons | $98.00 |
| 10x12 | 12 x 14 ft | 2.3 cubic yards | 3.08 tons | $112.70 |
| 10x16 | 12 x 18 ft | 3 cubic yards | 3.96 tons | $147.00 |
| 12x12 | 14 x 14 ft | 2.7 cubic yards | 3.59 tons | $132.30 |
| 12x16 | 14 x 18 ft | 3.5 cubic yards | 4.62 tons | $171.50 |
| 12x20 | 14 x 22 ft | 4.2 cubic yards | 5.65 tons | $205.80 |
| 12x24 | 14 x 26 ft | 5 cubic yards | 6.67 tons | $245.00 |
Stone this heavy is a bulk delivery, not a bag job: the pad for a 10x12 shed would take over 120 bags of 50 lb. Ask the supplier whether they sell by the yard or the ton and what the minimum load is.
Gravel pad, slab or blocks?
- Gravel pad with skids: the usual choice on flat or gently sloping ground. It drains, so the floor frame stays dry.
- Concrete slab: for a workshop with heavy machines, a shed you drive into, or a town that requires one.
- Concrete blocks: for a small shed on ground that slopes too much for a pad.
The shed foundation guide compares each one, and the gravel pad guide shows how to build the pad step by step and what it costs.
Concrete for a shed slab
Choose “Concrete slab” to get the concrete for a slab the size of the shed. A 10x12 slab 4 in thick takes 1.63 yd³ with 10% for waste, which is 74 bags of 80 lb mix. At that amount a ready-mix delivery is usually less work and often less money. The concrete calculator compares the two prices.
Blocks under the skids
A shed floor sits on pressure-treated skids running its length: one under each edge, and more in between so that none are over 5 ft apart. Blocks go under each skid about every 4 ft. A 10x12 shed has 3 skids with 4 blocks under each, 12 in all, and a 12x16 takes 20. That is one block per point on level ground. On a slope the low side needs stacks, so count those as you set them out.
Quick answers
How much gravel do I need for a 10x12 shed?
Order 2.3 cubic yards of 3/4 in crushed stone, about 3.08 tons. That makes a pad 12 x 14 ft, 4 in deep, with 10% extra for compaction.
How much gravel do I need for a 12x16 shed?
Order 3.5 cubic yards, about 4.62 tons, for a pad 14 x 18 ft and 4 in deep.
How deep should a gravel pad for a shed be?
4 in of compacted crushed stone is the usual depth for a storage shed. On soft or wet ground, 6 in makes a firmer base. For a 10x12 shed that means 3.5 cubic yards instead of 2.3 cubic yards.
How much bigger than the shed should the pad be?
A foot on every side, so the pad is 2 ft wider and 2 ft longer than the shed. The roof overhangs the walls, and this keeps the drip line on stone instead of splashing soil onto the siding.
What kind of gravel goes under a shed?
3/4 in crushed stone. Its angular pieces lock together when tamped. Pea gravel is round and keeps shifting, so it makes a poor base.
Does a shed need footings?
Most storage sheds sit on a gravel pad or on blocks, with no footings in the ground. Footings below the frost line are for sheds built on posts, for steep slopes, and for towns that require them, which is more common with larger buildings. Ask your building department before you choose. See do you need a permit for a shed? and the shed footings guide, which counts and prices piers for every size.